BUILDOUT TRACKER
The buildout, in numbers.
Two public datasets we keep an eye on. Both come from Lawrence Berkeley National Laboratory, and we update this page when a new edition is published.
LAST UPDATED NOVEMBER 2026
01 · DEMAND
Data centers use three times the power they did a decade ago.
US data centers used 58 terawatt-hours of electricity in 2014 and 176 in 2023, about 4.4% of the national total. Berkeley Lab projects between 325 and 580 by 2028, which would be 6.7% to 12% of all US electricity.
Source: Lawrence Berkeley National Laboratory, 2024 United States Data Center Energy Usage Report, December 2024.
ReportedProjected range
View as table
| Year | TWh |
|---|---|
| 2014 | 58 |
| 2023 | 176 |
| 2028 (projected) | 325 to 580 |
02 · SUPPLY
More power is waiting for a grid connection than the country has installed.
At the end of 2024, about 2,290 gigawatts of generation and storage sat in US interconnection queues. The entire installed fleet is about 1,280. The queue shrank in 2024 as projects withdrew and grid operators reformed their processes, and Berkeley Lab cautions that not all of this capacity will be built.
Source: Lawrence Berkeley National Laboratory, Queued Up, 2021 to 2025 editions. Figures are approximate and combine generation and storage at year end.
View as table
| End of year | GW in queue |
|---|---|
| 2020 | about 950 |
| 2022 | about 2,000 |
| 2023 | about 2,600 |
| 2024 | about 2,290 |
HOW WE READ IT
Power is the slowest layer to expand.
Demand for electricity from compute is compounding, while new supply waits years for a connection. That gap is where we expect scarcity to last longest, and it shapes where we look.
Next on this page: capital spending by the largest cloud companies, drawn from their filings.